K-350 Submersible Build Diary

Submersible Build Log

MBT

Main Tanks Ready to Fit.

Plumbing

Testing Scuba Tank Fit.

VIewports

Main Viewports Arrive.

Plumbing

Plumbing Dog Leg.

Electrics

Switch Panel Fitted.

Plumbing

Scuba Tanks.

Plumbing

Plumbing System Test.

MBT

Forward Main Tank On.

MBT

Aft Main Tank On.

Instruments

Inclinometer.

MBT

Main Tanks Sealed.

Bumpers

Bumper Mounting Bars Fitted.

MBT

Main Vent Pipe Fitted.

Motors

Rudder Pedals Modified.

MBT

Main Vent Valves Fitted.

Motors

Aft Motor Compensator piping.

Instruments

Cabin Pressure Gauge.

MBT

Aft Tank Hatch.

Instruments

Cabin Pressure Gauge.

Bumpers

Main Bumpers Complete.

Bumpers

Motor Bumpers Fitted.

Instruments

UW Radio Fitted.

Instruments

Inclinometer Modified.

Electrics

Blower Fitted.

Battery Pods

Battery Pod Leak Alarm.

Battery Pods

Cleaning Battery Pod Seals.

Plumbing

Scuba Tank Brackets Fitted.

Instruments

Temp\Humidity Gauges Fitted.

Life Support

CO2 Scrubber Assembled.

Electrics

12v Panel Installed.

Battery Pods

Battery Pods Sealed.